$950M
Total Budget
64
Total Schools
| Project Location | Project | Target Budget | Target Start Date | Target End Date | Project Category |
| Freedom ES | Fire Alarm Replacement | 250000 | 2026-06-01 | 2026-08-07 | Code or Safety |
| Doherty HS | Tennis Court Resurfacing | 215000 | 2027-05-27 | 2027-06-30 | LEA |
| Carver ES | Stage Curtain Replacement | 100000 | 2026-07-01 | 2027-08-01 | Building Infrastructure |
| Carver ES | Playground Improvement | 100000 | 2026-07-01 | 2027-07-30 | Site Improvements |
| Project Location | Project Name | Key Notes |
| Freedom ES | Fire Alarm Replacement | complete replacement of fire alarm system |
| Doherty HS | Tennis Court Resurfacing | Tennis resurfacing will be next summer |
| Carver ES | Stage Curtain Replacement | Stage curtain has reached the end of it's useful life and requires replacement |
| Carver ES | Playground Improvement | Playground Improvements for Preschool and for the area where the modular current sits |